Log, reconcile and fault-find energy and pulse totals
Finish with a commissioning record, a historical-data check and a fault-finding sequence that preserves the original readings.
Written course for development review; live pulse commissioning and recording pending.
Before you start
- Identify the exact model, firmware and fitted input modules. A PAS source list does not prove that every input exists on the meter.
- Read and save the current setups and required logs before changing sources, multipliers, tariffs or counters. Use an authorised training setup for programming exercises.
Keep one record for each source
The configuration record should let another technician trace a reported total back to its physical source and mathematical meaning. Use it for electricity as well as water and gas.
| Record | What to retain |
|---|---|
| Identity | Meter model, serial/asset identity, firmware, PAS version, external meter identity and fitted input module. |
| Signal and quantity | DI number, output type, pulse/KYZ mode, polarity, debounce; electricity direction or water/gas volume basis. |
| Scaling | Original pulse specification, converted units per pulse, source/target, multiplier and engineering unit. Record CT/PT meaning for electrical readings. |
| Baseline | Start/end timestamps, raw counts and accumulated totals; existing external-meter offset; any reset or replacement. |
| Recording | Selected log field, cumulative or interval definition, trigger, period, timezone, archive location and retained span. |
| Acceptance | Expected increment, observed increment, difference, test conditions, explanation and responsible reviewer. |
Choose what the historical record must answer
For consumption over time, a cumulative volume or energy field can be useful when its source, unit and multiplier are clear. Use successive differences to calculate interval consumption only while the total remains continuous. Preserve reset and configuration-change context.
Select a recording interval for the application and available memory. Five-minute, fifteen-minute and thirty-minute periods are choices, not a guarantee that the records meet a particular market or billing requirement. Confirm the selected quantity, alignment and retained rows.
For EM133-XM, inspect the intended Data Log 1, 2 or 3 parameter list and trigger destination; do not assume that a log number fixes its purpose. Use the separate Data Log 16 lesson for Billing/TOU daily profiles. If the desired volume field is unavailable in a recorder, resolve the supported route rather than substituting a similarly named electrical field.
Upload before clearing or repartitioning
Use Logs > Upload Logs and inspect the saved database: correct device, fields, units, timestamps, earliest/latest records and continuity. Save the current setups separately. Only a checked archive establishes what was preserved.
Energy totals, pulse counters, demand values and log files have different reset targets. Clearing logs is not a method of zeroing a water meter, and resetting a counter is not a method of fixing a bad pulse factor. Review the exact operation and its scope before any authorised reset or memory change.
Follow the symptom to the right check
Begin with identity and the full signal chain. Change one justified setting at a time on an authorised setup, then repeat a known-increment test. Do not tune a multiplier merely to conceal a signal problem.
| Symptom | Next discriminating check |
|---|---|
| No raw-count increment | Check external output activity, fitted input, compatible signal/rating, wiring diagram, source assignment and pulse width/rate. A successful Ethernet ping does not test the pulse input. |
| Raw count correct; volume wrong | Check units-per-pulse versus pulses-per-unit, L versus kL/m³, the target register and duplicate scaling. |
| Approximately twice the expected count | Check whether KYZ counts both edges while the source specification defines one pulse per cycle. Also investigate contact bounce; the ratio alone does not prove the cause. |
| Missing counts at higher rate | Check source pulse width/rate and input limits. Excessive debounce can suppress valid transitions. On EM13x the debounce setting is shared across inputs. |
| Volume changes but wrong channel moves | Trace DI, source entry and destination together; check duplicate or swapped assignments. |
| Totals differ but increments agree | Check commissioning offset and reset/replacement dates before altering scaling. |
| Correct live total; wrong history | Check recorder field definition, trigger/destination, timestamps, missing rows and whether cumulative values were incorrectly summed. |
| Electrical energy consistently scaled incorrectly | Check primary/secondary interpretation, CT/PT settings and read format before applying another multiplier. |
Final practice: calculate before you configure
Water exercise: output 10 L/pulse; start count 4,100; finish count 4,160. Expected increment: 60 pulses × 0.010 = 0.600 kL. Gas exercise: output 0.1 m³/pulse; 25 detected pulses. Expected increment: 2.5 m³. These calculations are the test expectations, not measured outcomes.
The proposed completion evidence is a setup readback, a matched known-increment comparison and an opened historical archive showing the intended field and period. If any part is missing, keep that part open in the commissioning record. Do not mark a missing pulse test successful because the PAS settings saved.
Limits and checks
- Worked values are teaching examples, not readings or settings from the demonstration meter. No live programming or pulse test is represented by this written lesson.
Check your understanding
The count is wrong. Should you adjust the multiplier until the total matches?
May you clear a counter to make a commissioning screenshot look tidy?
Sources
- Source 1. EM13x Installation and Operation Manual — Billing/TOU (opens in a new tab)
Printed pages 114–118 / PDF pages 117–121. Base-family procedure; XM capacity and units require the XM reference.
- Source 2. EM13x Installation and Operation Manual — digital inputs and counters (opens in a new tab)
Printed pages 100–101 and 105–106 / PDF pages 103–104 and 108–109.
- Source 3. PAS Getting Started — save setups and retrieve logs (opens in a new tab)
BG0337 Rev. A2, pages 10, 21–22 and 25. Upload Setups and Upload Logs are separate operations.
- Source 4. EM133 / EM133-XM Modbus Reference — energy and Billing/TOU (opens in a new tab)
BG0640 Rev. A1, PDF/printed pages 32–38, 65–66 and 77–80. Page 66 contains an inconsistent target-range label; it is not a programming instruction.
- Source 5. EM13x Installation and Operation Manual — logging and resets (opens in a new tab)
Printed pages 119–124 and 130–131 / PDF pages 122–127 and 133–134. Check the installed model before changing or clearing records.
- Source 6. EM133 / EM133-XM Modbus Reference — volume units (opens in a new tab)
BG0640 Rev. A1, PDF/printed page 80, F15: m3, CF, CCF; kL and MJ are XM entries.
- Source 7. PRO Series Installation and Operation Manual (opens in a new tab)
BG0612 Rev. A8, December 2024. PDF/printed pages 10–12 (modules), 64, 80, 118 and 138–139. Some appendix/target tables differ; use the current protocol alongside the main chapters.
- Source 8. PM180 Operation Manual (opens in a new tab)
BG0525 Rev. A7, April 2019. Printed pages 9, 22, 75 and 117–118 / PDF pages 10, 23, 76 and 118–119.
Revision and review details
| Revision | Change and reason | Review / supersedes |
|---|---|---|
| 20261108-energy-v1 8 November 2026 | Added electricity-first energy and water/gas pulse-register lessons. Explain model-specific capacity, correct units, PAS setup and consumption checks. | Primary-source and configured Product Master consultation completed; independent artifact review follows. None |