The EDL180 Portable Event & Data Logger puts the measurement and logging capabilities of a PM180 into a portable case. This page covers what the manufacturer's documents say about three parts of the EDL180: the case and its supply, the current sensors supplied with it, and the PM180 meter inside. For the batteries, see Looking after the EDL180 batteries.

What is supplied

The manual lists the supplied content as the EDL180 analyser, a carry bag, a power cable with an EU plug, a set of four voltage probes (yellow, blue, red and black) with crocodile connectors, four flexible current sensors according to the ordered model, and a USB type A to type A cable.

SATEC Australia's advice: check that the power cord supplied with your unit suits the outlet you will use, because the manual lists an EU-plug cord. Contact SATEC Australia if it does not.

Identify the current sensors

The manual says the four sensors are supplied according to the ordered model. The 30/300/3,000 A model requires a battery, which is not supplied; the 200 A model does not require a battery. The manual gives a different current setting for each:

  • 30–3,000 A coil: the nominal current is determined on the coil integrator by its scale switch, and must be set in the unit according to that selection.
  • 200 A clamp: the manual gives a specific nominal-current setting for this clamp, but its sensor output figures on pages 4 and 7 are not consistent.

SATEC Australia's advice: confirm the nominal-current (CT) setting for your sensor set with SATEC Australia support before recording.

The nominal current is set either on the RGM screen or through PAS. The EDL180 can work with flexible and clamp sensors that have a voltage output of up to 6 V AC. For a locally sourced sensor, the manual says to contact the manufacturer to confirm compliance and get instructions.

SATEC Australia's advice: before a survey, confirm which sensor set your EDL180 was supplied with, because the battery need and the current setting differ.

Supply, charging and conditions

The manual says to connect the EDL180 to an AC supply using the power supply cord provided and turn the power switch on. The UPS battery starts charging automatically once external supply is connected, whether the unit is switched on or not. The manual gives the supply rating as 90–264 V AC, 50–60 Hz. When fully charged, the UPS runs the EDL180 for over 4 hours at maximum consumption. The manual gives no charge time and no pre-survey checklist.

The manual's operating conditions are 0–60 °C and 0 to 95% humidity, non-condensing. The unit weighs 4.6 kg, or 6.9 kg with the carry bag, voltage probes and power cord.

Connection requirements in the manual

  • The distance between the EDL180 and the current lines must be at least half a metre for lines carrying up to 600 A, and at least one metre for currents between 600 A and 3,000 A.
  • The voltage probes connect to the 4 mm sockets marked V1, V2, V3 and VN, and to the conductors according to the wiring mode. The manual's warning: the voltage between phases (V1, V2, V3) must not exceed 828 V. Its introduction says the EDL180 is suitable for direct measurement of voltages up to 828 V AC, or greater when using a potential transformer.
  • The manual says to connect the current sensors' outputs first to the EDL180 and then to the measured circuits.
  • The wiring mode is the same as for the PM180. The EDL180 manual shows a four-wire WYE direct connection using three CTs; for other arrangements it refers to the PM180 Installation and Operation manuals.

On accuracy, the manual says: "The EDL180 accuracy is set by the combined accuracies of the PM180, current clamps and the PT, if used. The common factors are the unit accuracy and that of the current clamps, which are the dominant factor."

Prepare the PM180 inside

The EDL180 manual says device configuration is identical to that of the PM180, and refers to the PM180 manuals for configuration through PAS. The PM180 Operation Manual says:

  • Its Basic Setup menu table lists the wiring connection mode, PT ratios and secondaries, and CT primary currents. That table is written for the PM180's RDM display.
  • In PAS, Upload Setups copies the setup from the meter to the site database. Send writes one setup to the meter, and Download Setups writes all setups to it. Save as stores a setup prepared off-line in the site database. "Always set up and store the Basic Setup data to the site database first."
  • Logs > Upload Logs retrieves selected logs to the PC in MS Access database format, with optional From and To dates.
  • Monitor > RTC shows the PC time and the device time; Set synchronises the device clock with the PC clock. The manual adds that you need not update the clock if it is synchronised to an external GPS master clock.
  • Monitor > Reset clears energy accumulators, maximum demands, Min/Max registers, counters and log files.

SATEC Australia's advice: before changing anything for a new survey, upload the PM180 setup to a PAS site database and retrieve any logs you need to keep. Do not use Reset to clear logs until those records are saved.

SATEC Australia's advice: check the PM180 clock in PAS before recording, so event times can be compared with other records.

For general PAS file handling, see Upload the setups, then duplicate the backup in PAS; the lesson says its PAS file-management steps apply across models, while available programming menus differ.