PM175 PRO · REPLACEMENT CHECKS
Is the PM175 PRO a suitable replacement for my legacy PM175?

SATEC Australia's PM175 LED datasheet says: "The PM175 with LED display is no longer offered for new orders. It has been superseded by the PRO Series PM175, which adds Class A power quality measurement per IEC 61000-4-30." The PM175 PRO has its own manual, BG0657. This page lists the differences documented in the two manuals.
SATEC Australia's advice: don't treat the PM175 PRO as a drop-in replacement. Plan the change as a new installation, based on the existing meter's records, and confirm it with SATEC Australia before ordering.
Documented differences
| Item | Legacy PM175 (BG0415 Rev. A7) | PM175 PRO (BG0657 Rev. A2) |
|---|---|---|
| Panel cutout figures | "ANSI 4" round cutout" and "DIN 92x92mm square cutout" (Figures 2-2, 2-3) | "ANSI 4" round cutout" and "DIN 92x92mm square cutout" (Figures 3-2, 3-3) |
| Figure "Dimensions" labels | Figure 2-1: 127.0 MAX, 16.0, 114.0, 127.0 | Figure 3-1: 143.74, 103, 127, 127, 114.3, 19.8 |
| Power supply terminals | L/+ terminal 12, N/− terminal 10 | L/+ terminal 10, N/− terminal 9 |
| AC inputs | "3 voltage and 3 current transformer-isolated AC inputs" | "4 voltage and 4 current transformer-isolated AC inputs" |
| Built-in I/O | "2 digital inputs", "2 relay outputs"; optional analogue outputs, analogue inputs and analogue expander | "2 built-in digital inputs", "1 built-in relay output"; "Optional internal module (assembled internally during production)" |
| Communication ports | COM1: "RS-232/RS-422/RS-485", "56K Dial-up modem", "Ethernet 10/100BaseT"; COM2: "RS-422/RS-485"; the rear label drawing also has a PROFIBUS box | "Two Ethernet communication ports. 1 RS485 serial communication port"; "USB 2.0 port (type C)"; IRIG-B time sync input |
| Protocols | "Modbus RTU, Modbus ASCII and Modbus/TCP, DNP3 and DNP3/TCP (with firmware V25.2.01 and later)"; the SATEC Australia LED datasheet also lists Profibus DP | "Modbus RTU, Modbus/TCP, DNP3 serial, DNP3/TCP, IEC 60870-5-104 protocols and IEC 61850 Ed2 protocol"; RS-485 port: "MODBUS RsTU/ASCII, DNP3.0 and IEC 60870-5-101". Both PM17x PRO datasheets list IEC 61850 as an ordered option (order code 850) |
| Recording | "1 Mbyte RAM with battery backup"; "16 data recorders"; "Two waveform recorders" | "16GB Memory"; "Sixteen Fast Data recorders"; "Eight Fast Waveform recorders" |
| Display | Three-row LED; the SATEC Australia TFT datasheet lists a 5.7-inch touch-screen version | Three-row LED; can be ordered with "a LED Remote Display Module (RDM17X) or an LCD Remote Graphical Module (RGM180)" |
| PAS model | "PM175" | "PM17X PRO" |
Points to check
We found no Profibus in any page of the PM17X PRO manual or either PM17x PRO datasheet.
SATEC Australia's advice on each part of the change:
- Mechanical: check the depth and clearance behind the panel against the PRO dimension drawing.
- Wiring: wire from the PRO manual's own diagrams, and don't reuse the legacy terminal numbers.
- Supply: check the label on the unit you receive. See Which auxiliary supply rating applies to my PM175 PRO?
- Communications: if the existing PM175 uses Profibus DP, raise it with SATEC Australia before ordering. Where both meters support a protocol, take register maps, point lists and data formats from the PRO's own protocol guides. Don't assume a SCADA or BMS mapping carries over.
- I/O: count the relays, digital inputs and analogue signals the site uses before choosing the PRO's options.
- Setup: don't copy the legacy setup into a PRO site. Save the legacy meter's setup first, then prepare a new PRO setup from those recorded settings, checking each item against the PRO manual.
Before you remove the legacy PM175
SATEC Australia's advice: before removing the legacy meter, do these steps:
- Photograph the rear label, the wiring and the panel cutout.
- Read and save the meter's setup in PAS without sending anything to the meter. See Which PAS actions read from, save locally or write to my meter?
- Retrieve the recorded logs and keep a copy. See How do I retrieve recorded logs in PAS and keep the original data?
- Note the energy register readings and the date and time they were read.
- Record the communication settings used by any SCADA, BMS or data system connected to the meter.
Scope
This page compares the documented hardware and software only.
What to send SATEC Australia
SATEC Australia's advice: include these details when you ask about replacing a PM175:
- photos of the legacy PM175's rear label and wiring
- the saved PAS setup file, and a list of the I/O and communications in use
- the site supply voltage, and the CT and PT ratings
- the panel cutout, and the depth available behind the panel